hepman Posted April 8, 2008 Report Posted April 8, 2008 Dear All, I like to measure with PCI-6259 and DAQmx following scenario: There is a trigger with 1 kHz (1 ms) and between the triggers, Data(Ai0) have to be measured with maximal sampling rate 1.25 MS/s it should be 1000 Datapoints (1.25 MS/s -> 1000 points = 800µs) 200µs time left for next trigger-start. Is this possible and if yes how. Is there an example somewhere, i tried Labview examples but they don´t work. Best Regards Hepman Quote
jg69 Posted April 12, 2008 Report Posted April 12, 2008 Crossposted here: http://www.labviewforum.de/Trigger-mit-1-k...hmen-t9084.html and here: http ://forums.ni.com/ni/board/message?boar...d.id=38930 Quote